National Project · Pakistan

Karachi Gateway Terminal Quay / Ship-to-Shore Cranes

Ongoing maintenance and patch repair by Zinga Mosh Pakistan for quay cranes at Karachi Gateway Terminal Limited, associated with Noatum Ports and AD Ports Group. The project applies a specified multi-layer coating system to support corrosion protection in a marine environment.

C5-M Marine Quay Cranes Ongoing Maintenance
Customer Karachi Gateway Terminal Limited
Structure Quay / Ship-to-Shore Cranes
Location / Environment Karachi, Pakistan · C5-M Marine
Project Duration Since December 2023
Project Overview

Maintaining critical port crane infrastructure

Karachi Gateway Terminal Limited (KGTL), associated with Noatum Ports and AD Ports Group, operates in Karachi, Pakistan. Zinga Mosh Pakistan is carrying out ongoing maintenance and patch repair on quay cranes, also referred to as ship-to-shore cranes.

The supplied project details specify a C5-M marine environment and a coating system comprising ZINGA, ZINGATARFREE and an additional PU topcoat. Mechanical surface preparation to St 2 / St 3 is specified in accordance with ISO 8501-1.

The project began in December 2023, with a reported cumulative completed area of 2,000 m² as of August 2026.

Project Information

Customer Karachi Gateway Terminal Limited (KGTL) / Noatum Ports
Group AD Ports Group
Structure Quay Cranes (QC) / Ship-to-Shore Cranes
Location Karachi, Pakistan
Environment C5-M Marine · ISO 12944
Execution Ongoing maintenance and patch repair by ZMP
Project Duration Since December 2023
Area Completed 2,000 m² as of August 2026
Project Transformation

Before & After Coating

Compare the supplied before and after photographs. Drag the centre control to reveal the surface condition at each stage.

Karachi Gateway Terminal crane surface before coating Karachi Gateway Terminal crane surface after ZINGA duplex and local PU coating Before After
Before coating After coating
Surface preparation work on Karachi Gateway Terminal crane
Preparation & Application

Surface preparation before coating

Surface preparation is a key stage in the maintenance process. The project specification identifies mechanical preparation to St 2 / St 3 in accordance with ISO 8501-1 before application of the coating system.

Surface preparation · St 2 / St 3 · ISO 8501-1